Brooks's law
Adding people to a late software project makes it later
Communication paths calculator
people
people
Paths = people × (people − 1) ÷ 2
Now: 5 people
10 paths
After: 8 people
28 paths
Communication paths grow
2.8×
People grow 1.6×, but paths grow 2.8×
Everyday examples
A team of 5 grows to 10 → paths go from 10 to 45
Twice the people means 4.5 times as many pairs who need to keep each other up to date.
Nine women can't make a baby in one month
Brooks's own example of work that can't be split: some tasks take the time they take, no matter how many people help.
How accurate is it?
| People | Communication paths |
|---|---|
| 2 | 1 |
| 3 | 3 |
| 5 | 10 |
| 8 | 28 |
| 10 | 45 |
| 15 | 105 |
| 20 | 190 |
| 50 | 1,225 |
Brooks himself called it an "outrageous oversimplification"
The number of paths is exact math. How much extra people slow a project down depends on how long newcomers need to get up to speed and how well the work can be divided.
When it doesn't work
- Projects that are not late yet. Adding people early, before the final phase, can still help.
- Work that splits cleanly. Cleaning hotel rooms gets faster with more people — until they start getting in each other's way.
- Well-divided teams. With a good modular design, small groups mostly talk among themselves, so paths grow far less. Some suggest adding more people than seems necessary, and adding them early.
Why does it work?
Fred Brooks described it in The Mythical Man-Month (1975). He gave three reasons: new people need time to become productive and take time from experienced members who train them; the number of communication paths grows much faster than the number of people; and many tasks simply can't be divided.